New rules set fees for extra time on stalled and closed tourism properties

Regulation 2026/R-80 charges a USD 100,000 fee to extend a construction period and caps extensions at 12 months for islands and 24 for lagoons.

A new regulation published in the Government Gazette on 10 September sets out how the Ministry of Tourism handles leased tourism sites that are still undeveloped, properties closed for redevelopment, and the deferral of rent and fines on them.

To extend a construction period, a lessee must agree to complete and open at least one phase within the extension, pay the state a USD 100,000 fee and make a corporate social responsibility payment set by zone and island size. Extensions run from one month to a maximum of 12 months for islands and land plots, and 24 months for lagoons. Phased projects pay USD 300,000 for two phases and USD 400,000 for each extra phase. Fees are due within 30 days of conditional approval.

Partial closures for redevelopment are limited to 18 months, or up to 24 months if the whole property is demolished and rebuilt. A property that misses its reopening date can be given six more months for USD 300,000 or twelve for USD 600,000.

Separate provisions cover sites more than eight years past their development deadline with over USD 10 million owed to the state, including cancelling leases where no physical work has started.

Source: Government Gazette, Regulation 2026/R-80 (Ministry of Tourism and Civil Aviation).